£1.85m Development Finance for Four Houses in Dorchester, Dorset

Development Finance
4 min read

A £1.85 million senior development facility for four three-bedroom family houses on an infill site in Dorchester, Dorset, at about 69% of an approximate £2.7 million GDV. Clean planning, an efficient build and strong pre-sales interest made this a well-shaped deal, and the one thing that tested the programme was an archaeological watching brief that held up the foundations by several weeks and added to the professional fees.

Deal snapshot
Location Dorchester, Dorset
Loan amount £1,850,000 senior development facility
GDV (approx) Around £2,700,000
Loan to GDV (approx) About 69%
Project Ground-up build of four 3-bed houses on an infill site
Planning route Planning permission in place, with no complications
Exit Sales of the completed houses

The situation

Our client came to us with an infill plot in Dorchester and a consent for four three-bedroom houses, the kind of family home the county town never seems to have enough of. The planning permission was clean, and on an infill site that is worth a great deal, because these plots usually sit between existing homes and the neighbours tend to have plenty to say before a decision notice is issued. Here that work had already been done and nothing in the consent worried us when we read it through.

The requirement was £1.85 million of development finance against a gross development value of around £2.7 million, which put the facility at about 69% of GDV. That is a sensible level for a small ground-up scheme, and it meant we could present the case to lenders without having to stretch any of the numbers to make it fit.

The scheme

Four houses is a scale I like, because the build is simple enough for one contractor to manage closely and the sales risk is spread across a handful of homes that all appeal to the same local buyer. Dorchester has steady demand from families who live and work in the area, and three-bedroom houses sit right in the middle of that market.

The exit was always going to be sales of the completed homes, and local demand for family houses supported that exit from the first conversation. On a scheme of this size I want to be able to picture who is going to buy each house, and in this case that was easy.

What went well

The build programme ran efficiently, and the pre-sales interest was strong. On a sales exit, early interest from buyers changes the risk profile of the whole facility, because every house that has a buyer lined up before practical completion is one less the developer has to sell against the clock while interest is still running.

What I have noticed over the years is that a credit team reads a small scheme with real buyer interest very differently from one where the sales are still a line in a spreadsheet. Buyer interest gives them something concrete to point at when they sign off the exit, and on a four-unit scheme that is often the comfort they are looking for.

The challenge

The archaeological watching brief was the part of this deal that tested everyone. Dorchester has a long history and sites in and around the town can attract an archaeology condition on the planning consent. As general context, a watching brief means an archaeologist attends site while the ground is opened up and records anything of interest, and if something significant turns up the groundworks can pause while it is dealt with.

On this site the watching brief delayed the foundations by several weeks and increased the professional fees. Neither is fatal on a scheme of this size, although both come straight out of contingency, and a delay at foundation stage pushes every later stage of the build back with it. Anyone buying a development plot in a historic town needs to read the archaeology condition carefully before they buy, and needs to build time for it into the programme and money for it into the cost plan.

How this type of facility works

A senior development facility on a small housing scheme generally works in two parts. A day-one advance goes towards the land, and the build money is released in stages as the houses go up, with a monitoring surveyor visiting site and certifying each stage before funds are drawn. Interest is usually charged only on what has been drawn, so the cost of the facility builds gradually through the programme. That is the general shape of the product, and the detail on any facility depends on the lender, the site and the developer.

The point I make to every developer on a ground-up scheme is that the programme in the appraisal is a target, and the facility needs enough time in it to absorb something like a watching brief without the developer being forced to sell the last house in a hurry. Development finance is priced on time, so a realistic programme at the start costs far less than an extension negotiated halfway through.

The outcome

The four houses were built on the £1.85 million facility, the build ran efficiently once the foundations were in, and strong pre-sales interest supported a smooth exit through sales into a local market that wants exactly this type of home. The archaeology cost several weeks and some extra professional fees, and the scheme still delivered what the planning, the location and the demand had promised.

The outcome

A £1.85 million senior development facility at about 69% of an approximate £2.7 million GDV for four family houses on an infill site in Dorchester. Clean planning, an efficient build and strong pre-sales interest supported a smooth exit through sales, with an archaeological watching brief the one real issue, delaying the foundations by several weeks and adding to the professional fees.

Frequently asked questions

What does an archaeological watching brief mean for development finance?

A watching brief is a planning condition that requires an archaeologist to attend site during groundworks and record anything found. It rarely stops a scheme, but it can slow the foundation stage and adds professional fees, so lenders want to see the condition reflected in the programme and the cost plan, and developers should hold enough contingency and facility term to absorb a delay.

How do staged drawdowns work on a small ground-up housing scheme?

Most senior development lenders advance part of the land cost on day one and release the build money in stages. Before each release a monitoring surveyor visits site, checks the work against the cost plan and certifies the drawdown. Interest is normally charged only on the funds drawn, so the cost of the facility builds gradually through the programme.

How much can I borrow against GDV on a small housing scheme?

Senior development lenders typically work to a maximum of around 60% to 70% of GDV, alongside a separate limit on the share of total project costs they will fund. Where a scheme sits within those limits depends on the land value, the build costs, the developer’s experience and the strength of the local sales evidence.

Completed transaction. This case study describes a live deal arranged by Fox Davidson. Client details are anonymised and figures rounded.

Rates and lending criteria are subject to change by lenders without notice. Your property may be repossessed if you do not keep up repayments on a mortgage or any other debt secured on it.

We arrange senior development finance from £250,000 across England, Scotland and Wales, including small housing schemes in Dorset where the planning conditions need as much attention as the numbers.