A £3.8 million senior development facility for seven three and four-bed houses in Maidenhead, with a gross development value of around £5.7 million that puts the loan at about 67% of GDV. Strong Thames Valley demand and a contractor who performed well were the strengths of the scheme, while flood-risk mitigation and sequential drainage design added engineering costs nobody had planned for and delayed the start.
| Location | Maidenhead, Berkshire |
| Loan amount | £3,800,000 |
| GDV (approx) | Around £5,700,000 |
| Loan to GDV (approx) | About 67% |
| Project | Ground-up build of 7 three and four-bed houses |
The situation
Maidenhead sits in the middle of the Thames Valley, with good links into London and Reading and steady demand for family homes. The client was building seven houses, a mix of three and four bedrooms, and the senior facility was £3.8 million against a finished value of around £5.7 million.
Family houses in the Thames Valley are a product lenders understand well, and the demand side of this case was never in doubt. The question a credit team asks on a scheme like this is whether the site can be built out on time and on budget, and on a site near the Thames that question usually starts with water.
The challenge
Flood-risk mitigation and the sequential drainage design that went with it added engineering costs that had not been expected and delayed the start on site. Drainage on a flood-sensitive site has to satisfy the council before work can begin, and once the engineers start working through the design the scope has a habit of growing.
A delayed start matters on development finance because the land is usually bought and funded before the first spade goes in, and the clock on the facility is running from that point. What I advise on any site with flood or drainage questions is to get the engineering done early, ideally before the facility completes, and to build some slack into the term so that time lost at the start do not turn into pressure at the end when the houses are being sold.
Unexpected engineering costs also eat into contingency before the build has properly begun, which leaves less cover for anything that goes wrong later. A lender will look at that closely, so the cost plan needs updating as soon as the drainage design changes.
What went well
Demand for family homes in the Thames Valley was strong, which supported the values and gave the exit a solid footing. The contractor also performed well, and on a ground-up scheme that is worth a great deal.
The contractor is as much a part of the lending decision as the site. A good contractor keeps to the programme, produces work the monitoring surveyor is happy to certify and keeps the drawdowns flowing month by month, and once a scheme has had a slow start, a builder who makes up ground is the best protection the developer has.
How the finance was structured
In general terms, a senior development facility on a scheme like this funds part of the land on day one and releases the build costs in monthly stages, each certified by a monitoring surveyor who checks the work on site against the cost plan. Interest is charged on what has been drawn, so the cost of the facility grows with the build, and the loan is repaid as the finished houses are sold or refinanced.
Where there is a known risk on drainage or flooding, we make sure the lender sees the flood risk assessment, the drainage strategy and the engineer’s costs up front, because a credit team that has seen the problem and the plan for dealing with it is far more comfortable than one that finds it in the valuation report.
The outcome
The scheme delivered seven three and four-bed houses with a GDV of around £5.7 million, funded by a £3.8 million facility at about 67% of GDV. Flood-risk mitigation and the drainage design added cost and delayed the start, and strong Thames Valley demand and good contractor performance kept the project on course after that.
Sites near rivers are not a reason to walk away from a scheme, and the Thames Valley would have very few new homes if they were. They do need the engineering taken seriously at the appraisal stage, with a drainage engineer involved before the cost plan is signed off, and I would always rather a client spends on that advice early than finds the cost once the facility is running.
The outcome
A £3.8 million senior development facility at about 67% of GDV funded seven three and four-bed houses in Maidenhead with a GDV of around £5.7 million. Flood-risk mitigation and sequential drainage design added engineering cost and delayed the start, and strong Thames Valley demand with good contractor performance carried the scheme.
Frequently asked questions
How does flood risk affect development finance?
Lenders will fund sites in flood risk areas where planning has been granted with the right mitigation, but they look closely at the flood risk assessment, the drainage strategy and whether the finished homes will be insurable and mortgageable for buyers. Mitigation and drainage costs should be in the appraisal from the start.
Why does the contractor matter to a development lender?
The lender’s monitoring surveyor reviews the contractor’s experience, the building contract and the cost plan before the facility completes, and checks progress before each monthly release. A contractor with a good record makes the build programme more believable, which supports both the terms offered and the smooth running of the drawdowns.
What happens if the start of a development is delayed?
If the facility has completed and the land advance has been drawn, interest runs on that balance while the site waits, so a delay uses up part of the term and eats into profit. Where a delay is possible, for example on drainage or flood conditions, it makes sense to build extra time into the term or to complete the facility once those matters are close to being resolved.
Completed transaction. This case study describes a live deal arranged by Fox Davidson. Client details are anonymised and figures rounded.
Rates and lending criteria are subject to change by lenders without notice. Your property may be repossessed if you do not keep up repayments on a mortgage or any other debt secured on it.
We arrange senior development finance from £250,000 across England, Scotland and Wales, including Maidenhead and the wider Thames Valley, with site risks such as drainage and flooding set out for lenders before they ask.
*Minimum loan for Scotland bridging, commercial and development finance cases is £1,000,000, on mainland Scotland in and around Glasgow, Edinburgh and other major cities. We do not arrange finance in Northern Ireland.