£4.2m Development Finance for Six Detached Houses in Woking

Development Finance
4 min read

A £4.2 million senior development facility for six four bed detached houses in Woking, Surrey, at about 65% of a GDV of around £6.5 million. A commuter belt scheme where strong off-plan reservations and good build quality helped the developer reach the target GDV, against a high site cost, rising material prices and drainage attenuation works that were more complex than expected.

Deal snapshot
Location Woking, Surrey
Loan amount £4,200,000
GDV (approx) Around £6,500,000
Loan to GDV (approx) About 65%
Project Ground up build of six four bed detached houses
Exit Sales, supported by off-plan reservations

The situation

Woking is commuter belt in the truest sense, with fast trains into London and a steady supply of buyers looking for a detached family house within reach of the capital. The client was building six four bed detached houses from the ground up, and we arranged a senior development facility of £4.2 million against a gross development value of around £6.5 million, putting the loan at about 65% of GDV.

This was a sought-after scheme from the start, and the appeal to buyers was obvious. The pressure on the deal came from the other end of the appraisal, where the cost of getting into the site and the cost of building on it both moved against the developer.

The squeeze on margin

The site acquisition cost was high, which is the norm in this part of Surrey, and rising material prices squeezed the margin further once the build was under way. Land in the commuter belt is priced for what the finished houses will sell for, so there is rarely much slack left for the developer, and when timber, steel, blocks and the rest move up during a build the profit is the first number to give.

Over the years I have learned that a squeezed margin worries a lender far less than a surprised one. A credit team can live with a thinner profit if the GDV is well supported and the developer has shown how the extra cost is being met, and what they do not like is finding the problem for themselves in a monitoring report. That is where we add real value, keeping the lender up to date before a cost change becomes a question.

Drainage attenuation

The drainage attenuation works turned out to be more complex than expected. In general terms, attenuation is how a new development holds back surface water during heavy rain and releases it slowly, so the site does not send more water into the drains or watercourses than the ground did before it was built on. It is usually done with underground tanks or crates, ponds or swales, sized to the site and agreed with the council and the drainage authority.

Attenuation is one of those parts of a scheme that looks simple on the drawings and becomes harder once the ground is opened up and the levels, the soil and the outfall are tested properly. I always tell clients to treat the drainage design as an early job, because it affects levels across the whole site and it is expensive to change later.

How the facility was set up

I will describe this in general terms. A senior development facility on a ground up scheme usually advances part of the land cost on day one and releases the build money in monthly stages, each one certified by a monitoring surveyor who visits site and checks the work against the cost plan. Interest is charged on what has been drawn, so the cost of the money builds as the houses go up, and the facility is repaid from sales of the completed homes.

On a six house scheme the lender is also looking hard at the quality of the build, because the valuer has to stand behind the GDV at the end, and four bed detached houses in an area like Woking are bought by people who know exactly what they expect for the money.

What went well

The scheme had strong off-plan reservations, and good build quality helped achieve the target GDV. Off-plan interest on a scheme like this tells the lender the market is there before the houses are finished, and it gives the valuer real evidence to work from instead of comparables from other sites.

Build quality sells houses at this level. The developer kept the standard high while costs were rising, which is hard to do and exactly what protected the end values, and those values are what repay the facility.

The outcome

A £4.2 million senior development facility at about 65% of a GDV of around £6.5 million for six four bed detached houses in Woking. The high land cost, rising material prices and complex drainage attenuation squeezed the margin, and strong off-plan reservations and good build quality helped the scheme achieve its target GDV.

Frequently asked questions

How do staged drawdowns work on a ground up development?

The lender usually advances part of the land cost on day one and releases build funding in stages, typically monthly, after a monitoring surveyor has visited site and certified the work completed against the cost plan. Interest is charged on the funds drawn, so the finance cost builds gradually as the scheme progresses.

Do off-plan reservations help with development finance?

They help. Reservations show the lender and the valuer that there is real demand for the finished homes at the expected prices, which supports the GDV and reduces the perceived risk of the sales exit. Most lenders will still assess the scheme on its full appraisal, but credible reservations strengthen the case.

What is drainage attenuation on a housing development?

Attenuation is the way a development stores surface water during heavy rain and releases it at a controlled rate, so the site does not discharge more water than it did before it was developed. It is usually achieved with underground tanks or crates, ponds or swales, and the design has to be agreed with the council and the relevant drainage authority.

Completed transaction. This case study describes a live deal arranged by Fox Davidson. Client details are anonymised and figures rounded.

Rates and lending criteria are subject to change by lenders without notice. Your property may be repossessed if you do not keep up repayments on a mortgage or any other debt secured on it.

We arrange senior development finance from £250,000 across England, Scotland and Wales, including ground up housing schemes in Surrey and the commuter belt around London.

Call 03300 100313

*Minimum loan for Scotland bridging, commercial and development finance cases is £1,000,000, on mainland Scotland in and around Glasgow, Edinburgh and other major cities. We do not arrange finance in Northern Ireland.

Get in Touch

Recent case studies

Loading...

Get in Touch