A £1.15 million conversion facility to turn a former office building in Poole, Dorset into six flats, at about 66% of a GDV of around £1.75 million. The prior approval route kept the costs under control and the location sold the flats quickly, while unplanned strengthening of the existing frame and a parking negotiation with the council were the two issues the scheme had to absorb along the way.
| Location | Poole, Dorset |
| Loan amount | £1,150,000 |
| GDV (approx) | Around £1,750,000 |
| Loan to GDV (approx) | About 66% |
| Project | Former offices converted into six flats |
| Planning route | Prior approval |
| Exit | Sales of the completed flats |
The situation
The client had a former office building in Poole and a plan to turn it into six flats. What stood out about the building was how close it sat to the shops, transport and everyday amenities that buyers of smaller flats want on their doorstep, which told me early on that the exit was likely to be the easiest part of this deal. We arranged a facility of £1.15 million against a gross development value of around £1.75 million, so the loan sat at about 66% of GDV.
Office conversions in the coastal towns of Dorset come across my desk fairly often, and a lender’s questions on them usually settle on whether the change of use stands up, whether an old commercial structure is fit to become homes and how quickly the finished units will sell. On Poole the planning and the sales case were both strong, and the structure was the one that tested everybody.
Why the prior approval route suited this building
The scheme went through prior approval instead of a full planning application, and that kept the costs controlled. In general terms, prior approval for office to residential, now usually under Class MA, allows a building in commercial use to become homes without full planning permission, with the council limited to assessing a set list of matters such as transport, contamination, flood risk, noise and natural light to each habitable room. The council cannot reopen the principle of the change of use once the route applies, and that certainty is something credit teams at development lenders like to see because it removes one of the bigger planning risks from the appraisal.
Prior approval is not always the best solution for every office building, because the finished flats still have to meet space and light standards, and some buildings simply do not lay out well. This one did.
The challenge: the frame and the parking
Two things went against the scheme. The existing frame needed structural strengthening that nobody had expected, and the parking provision for the new flats had to be negotiated with the local authority. Transport is one of the matters a council can look at under prior approval, so parking is a fair thing for officers to raise even when the residential use itself is settled, and on a town centre site with limited space those conversations take time and goodwill on both sides.
What we have seen across office conversions is that the existing structure is where the surprises hide. Office buildings were designed for different loads, layouts and services than flats, and a survey can only see so much until the ceilings and partitions come out. This is why I push every conversion client to carry a proper contingency in the cost plan and to treat it as money that will probably be spent, and why I want the lender’s monitoring surveyor kept close to anything that changes in the works.
How conversion finance is usually put together
I will keep this part general, because the shape of a conversion facility is broadly the same from scheme to scheme. A development lender normally advances part of the purchase price on day one and then releases the works money in stages as the conversion progresses, with a monitoring surveyor visiting site and certifying the work before each drawdown. Interest is usually charged on what has been drawn, and the loan is sized against both the total cost of the scheme and the GDV, which is why the loan to GDV figure appears on every term sheet.
When something unexpected turns up in the structure, the lender will want to understand the extra cost and how it is being funded before the next stage releases. Once I understand the problem my role is to make sure the lender, the monitoring surveyor and the client are all working from the same cost picture, and I can save my client a lot of time by doing that work before anyone has to ask.
The sales
The location did exactly what we thought it would. Being near amenities, the completed flats sold quickly, and a quick sales period at the end of a conversion is what every development lender wants, since sales are the exit the facility is built around and every week a finished unit sits unsold is a week of interest running on.
Location sells flats. Good finish and a sensible price help, but a buyer looking at a one or two bedroom flat in a town like Poole is buying the walk to the shops and the station as much as the flat itself, and the valuer knows that too.
The outcome
A £1.15 million conversion facility at about 66% of a GDV of around £1.75 million, turning former offices in Poole into six flats. The prior approval route kept costs controlled, the structural strengthening and parking negotiations were worked through, and the completed flats sold quickly on the strength of their location near amenities.
Frequently asked questions
What is prior approval for office to residential conversion?
Prior approval is a permitted development route, now usually under Class MA, that lets a building in commercial use change to residential without a full planning application. The council can only assess a set list of matters, including transport, contamination, flood risk, noise and natural light to habitable rooms, and cannot refuse on the principle of residential use if the building qualifies.
Will a development lender fund an office conversion under prior approval?
Yes. Development lenders regularly fund office to residential schemes that have prior approval in place. They will look closely at the building survey, the cost plan and the contingency, and at sales evidence for flats of a similar size nearby, because the existing structure and the exit are where most of the risk sits on a conversion.
What happens if a conversion runs into unexpected structural works?
The client and the contractor price the extra works and the lender monitoring surveyor reviews the change against the cost plan. The cost is usually met first from the contingency, and if it goes beyond that the lender will want to see how the gap is funded before releasing further drawdowns, which is why an honest contingency matters from the start.
Completed transaction. This case study describes a live deal arranged by Fox Davidson. Client details are anonymised and figures rounded.
Rates and lending criteria are subject to change by lenders without notice. Your property may be repossessed if you do not keep up repayments on a mortgage or any other debt secured on it.
We arrange conversion finance from £250,000 across England, Scotland and Wales, including office to residential schemes in Dorset and the South West, and we work the structure around the building as it really is.
*Minimum loan for Scotland bridging, commercial and development finance cases is £1,000,000, on mainland Scotland in and around Glasgow, Edinburgh and other major cities. We do not arrange finance in Northern Ireland.